Case Law Update
Demasol Limited v South Pacific Industrial Limited [2022] NZCA 480
The Court of Appeal has confirmed the court's approach to payment claims and payment schedules in circumstances where a statutory demand has been issued.
Background
The case concerned a dispute between South Pacific Industrial Limited (SPI), the head contractor, and Demasol Limited, its subcontractor.
Demasol had served two payment claims alleging sums were due for extra work performed. SPI did not provide a payment schedule in response. Instead, it sent Demasol a letter denying that any sum was due, though later agreed to make a partial payment.
Demasol issued a statutory demand for the unpaid amounts. SPI applied to the High Court to have the demand set aside.
The decisions
A statutory demand may be set aside where the court is satisfied that there is a "substantial dispute" as to whether or not the debt is owing or is due. In the High Court, the associate judge set aside Demasol's statutory demand on the basis it was reasonably arguable that the relevant payment claims were invalid, as they had not been issued in accordance with a particular term of the parties' contract, or because the amount claimed related to variations that were arguably not authorised.
The Court of Appeal reversed that decision. It confirmed that the only enquiries required in relation to SPI's application to set aside the statutory demand were:
-
whether the relevant payment claim (by this point, only one claim remained in dispute) complied with s 20 of the Construction Contracts Act 2002 (CCA); and
-
if so, whether SPI had either (1) provided a payment schedule contesting its liability; or (2) paid the amount claimed by the due date.
The Court held that the general merits of Demasol's payment claim were not open for consideration and were irrelevant in the statutory demand context. Here, the payment claim had complied with the statutory requirements of the CCA. In response, SPI had neither provided a payment schedule contesting the claim, nor paid the amount claimed. Under s 23(1) of the CCA, Demasol was accordingly entitled to recover from SPI the unpaid portion of the claimed amount, together with its actual and reasonable costs of recovery.
The Court of Appeal further said:1
This consequence may seem harsh, but it is mandated by the CCA. We agree with the conclusion reached by Asher J in Marsden Villas Ltd v Wooding Construction Ltd [[2006] NZHC 569; [2007] 1 NZLR 807 (HC)], where the Judge commented as follows:
"The Act sets up a procedure whereby requests for payment are to be provided by contractors in a certain form. They must be responded to by the principal within a certain time frame and in a certain form, failing which the amount claimed by the contractor will become due for payment and can be enforced in the Courts as a debt. At that point, if the principal has failed to provide the response within the necessary time frame, the payment claimed must be made. The substantive issues relating to the payment can still be argued at a later point and adjustments made later if it is shown that there was a set-off or other basis for reducing the contractor’s claim.
[…]
As far as the principal is concerned, the regime set up is “sudden death”. Should the principal not follow the correct procedure, it can be obliged to pay in the interim what is claimed, whatever the merits. In that way if a principal does not act in accordance with the quick procedures of the Act, that principal, rather than the contractor and sub-contractors, will have to bear the consequences of delay in terms of cash flow."
Conclusion
While the appropriate treatment of payment claims and schedules under the CCA is well established, this case provides useful confirmation that, even where a statutory demand has been served on the non-paying party, the strict requirements of the CCA will continue to be applied.