New Zealand
Beca Carter Hollings & Ferner Limited v Wellington City Council [2022] NZCA 624
A recent decision of the Court of Appeal has addressed the relevant limitation period for contribution claims.
Background
CentrePort Limited operated the port at Wellington. In October 2006, it contracted with the BNZ to construct a building on land it owned on Waterloo Quay. CentrePort then contracted with Beca Carter Hollings & Ferner Ltd (Beca) for engineering and design consultancy services, and with Fletcher Construction Company Ltd for design and construction services. When the building was completed, it was leased by BNZ pursuant to the terms of the contract.
During the Kaikoura earthquake of November 2016, the building suffered irreparable damage. BNZ was never able to return to the building, which was determined uneconomical to repair and demolished.
Court proceedings
In August 2019, BNZ filed proceedings against Wellington City Council. It said the Council was liable to it in negligence because of the circumstances in which the Council had issued building consents and code compliance certificates.
The Council denied liability and pleaded a number of limitation defences. It also filed third party proceedings against Beca for contribution, in the event it was found liable to BNZ.
Beca denied any liability. It also considered that it was protected by the 10 year "long stop" period included in the Building Act 2004. On the basis that provision applied, the Council was out of time to bring a contribution claim against Beca.
Beca then applied for strike out and summary judgment. The High Court dismissed those applications. Amongst other things, it held that the Building Act's long stop provision did not apply to contribution claims. Beca appealed to the Court of Appeal.
The limitation issue
The main issue for the Court on appeal was whether the High Court was correct to find that the Building Act's 10 year long stop did not apply.
The Building Act’s long stop provision states: 1
… no relief may be granted in respect of civil proceedings relating to building work if those proceedings are brought against a person after 10 years or more from the date of the act or omission on which the proceedings are based.
Beca said that the Council’s claim for contribution was a civil proceeding relating to building work based on Beca’s allegedly negligent acts in 2007 and 2008. It said this meant that (1) the long stop provision applied; and (2) when the proceeding was commenced by the Council in 2019, its claim against Beca was out of time.
The Council argued the opposite. It said the Building Act long stop did not apply to claims for contribution. Instead, it considered that limitation for contribution claims was governed by s 34(4) of the Limitation Act 2010, which provides:
It is a defence to [a tortfeasor (A)’s] claim for contribution from [another tortfeasor (C)] if C proves that the date on which the claim is filed is at least 2 years after the date on which A’s liability to [another person (B)] is quantified by an agreement, award, or judgment.
The Council said that, because its own potential liability to BNZ had not yet been quantified by agreement, award or judgment, the two year limitation period had not yet begun, and the contribution claim could not be time barred.
Decision
The Court of Appeal held:
-
The long stop provision of the Building Act was not intended to apply to contribution claims.
-
The cause of action for a contribution claim accrues on the finding of liability; that is, the date upon which the person claiming contribution has been found liable to the original plaintiff.
-
From this date, a two year limitation period will apply.
-
The Council’s claim for contribution from Beca was accordingly not time barred.
The court's reasons included:
-
The relevant legislative history provided very strong support for the Council’s reasoning. That is, the introduction of the long stop period in the Building Act did not alter the law regarding contribution claims as it had been set out in the earlier Limitation Acts.
-
The phrasing of the Building Act, which refers to “the date of the act or omission on which the claim is based” is ill suited to contribution claims, which do not accrue at the time of the original wrongdoing.
-
Section 34 of the Limitation Act 2010 was intended to provide a “bespoke approach” in relation to contribution claims, which the Building Act did not override.
-
While there had been some prior High Court authority which supported Beca’s position, the Court considered that line of cases to be incorrect.
Observations
Claims for contribution can be an effective tool for reducing liability where another party may also be at fault.
There is benefit in initiating claims for contribution early:
-
Initiating contribution claims while the original claim remains on foot will give all parties a clearer sense of the potential complexity of the dispute. This may help to move matters towards settlement. It may also mean there is a greater pool of financial resources from which to draw in reaching a settlement.
-
It can mean one trial instead of two, saving time and money.
-
Where a claim for contribution is filed before judgment on the original claim is determined, the contribution claim – at least on the law as it now stands – will never be out of time.
However, as established by this case, claims for contribution need not be rushed.
It is, of course, possible that the decision will be appealed to the Supreme Court.
Contributors: Joanna Trezise & Jasleen Oberoi