Industry Spotlight
Supply chain delays in the construction industry
The results of the 2020 Russell McVeagh Construction Survey highlighted an industry concern of supply chain disruption to come, in light of the continuing effects of COVID-19 internationally. This concern has proved to be well-founded, with delays in the supply of construction materials throughout New Zealand over recent months, and significant backlogs seen at the ports.
It is important for those involved in construction projects to understand which contractual terms under NZS 3910:2013 and similarly worded contracts may be relevant, and how parties could address such issues when they arise.[1]
Extensions of time
Where supply of materials is delayed, a contractor may seek an extension of time. A number of qualifying events might be relied on:
The delay was not reasonably foreseeable (cl 10.3.1(f)).
This is the most obvious claim a contractor might make. The extent to which this clause applies will depend upon the exact reason for the delay and what was foreseeable when the contract was tendered for. If the cause of delay relates to COVID-19, and tendering for the contract occurred during 2020, it will be important to be clear on exactly what was (or should have been) understood about COVID-19 and its likely ramifications at that time. There are timelines of key events available online which may be useful in assessing this.[2]
When establishing what was reasonably foreseeable, it can be useful to draw from the law of negligence, where 'reasonable foreseeability' is a key concept in determining the scope of damage for which a defendant may be liable. In that context, a foreseeable risk is a “real risk”, being “one which would occur to the mind of a reasonable man in the position of the [defendant] and which he would not brush aside as farfetched.”[3] One might therefore ask: is this a risk a competent contractor might have priced for? If so, cl 10.3.1(f) is unlikely to apply.
If it is established that cl 10.3.1(f) does apply, the contractor would be entitled to time, but not to time-related costs (cl 10.3.6).
The net effect of any Variation (cl 10.3.1(a)).
There are a number of ways this clause might be relied upon. For example, if the goods were ordered to perform extra work requested by the Principal, the delay might be said to be part of the “net effect” of that Variation. If they were ordered following the late issue by the Engineer or Principal of any instruction, documents or Drawings, a similar argument might be made (cl 2.7.7). In some circumstances, where the delay relates to a nominated subcontractor supplier, this may also lead to it being considered as the net effect of a Variation (cl 4.2.6). Such delays would entitle the contractor to both time and to time-related costs (cl 10.3.6).
Other possibilities
There are other clauses which might be said to apply, depending on the precise facts. For example, in some cases the delay might be said to be due to a “Default of the Principal” (cl 10.3.1(g)), or the result of a new statute, regulation or bylaw (cl 5.11.10). Manufacturing delays or delays due to port backlog, however, are unlikely to trigger these provisions.
In each case, if the delay in supply continues, the contractor may need to give more than one notice (cl 10.3.3).
If the delays could have been avoided, the Engineer may take the view that an extension of time is not one to which the contractor is “fairly entitled” (cl 10.3.1). The parties' ability to reduce the impact of the delay in provision of those particular materials should therefore be carefully considered. Have sufficient investigations been made as to whether there could be an alternative source for the materials? Is there another, more readily available, material which the parties can agree is suitable for substitution?
Sometimes there may be no applicable clause under which a contractor can seek an extension of time. In those cases, it will simply fall to the contractor to bear the burden of the delay.
Frustration of contract (cl 14.1)
If the delay is considerable, and the relevant materials critical to performance of the contract, a party might claim that the contract has become impossible of performance, and therefore “frustrated” under cl 14.1. Alleging frustration, and seeking to terminate a contract, are significant steps and should not be taken without first seeking legal advice.
Tendering practice now
The possibility of supply chain delays is one of many risks that parties should now always consider at the time of tendering for a new project. Parties may wish to explicitly discuss and agree upon a process to be followed in the event of specified delays. One possibility is adding a substitution clause to their contract, by which the parties agree, in the event materials are unavailable or their supply considerably delayed, through no fault of either party, certain substitutions will be permissible.
Contributors: Michael Taylor and Joanna Trezise